Drainage Project – Weekly Reports

Pct. 1 Commissioner Terry Cook provides weekly updates of project progress (Map of work zones). 2021-2022 Reports: January 28, 2022 - January 21, 2022 - [...]

July 2021 Drainage Project Report

Williamson County has posted the July 2021 Project Report - visit the Forest North Drainage Improvements webpage to read report and view map of work [...]

Forest North Drainage Project – February 2021

Williamson County -- February construction update Letter with information as project moves to Phase III, which includes Newberry - Woodvale - Shasta [...]

Forest North Drainage Project Continues

As the Drainage Improvement Project moves to new zones around the neighborhood, please continue to watch for large equipment and vehicles on our streets. [...]

Forest North Drainage Project: 11-24-2020 Letter

Work is expected to begin in the Newberry Zone in December and in the Shasta Zone in early 2021.Please visit the Forest North Drainage Improvement Project [...]

Forest North Drainage Improvement Project – Letter Announcing Phase III Work

May 20, 2020Dear Neighbor, Williamson County is moving forward with the final phase of the Forest North Drainage Improvement Project. Work began in the [...]

Forest North Drainage Project – March 22, 2018 Update

The Forest North Drainage Improvements website continues to post updates about the project:Work in the Bayswater Zone has been completed by Williamson County [...]

Forest North Drainage Project – October 31, 2017 Update

Work in the Bayswater Zone has been completed by Williamson County Road and Bridge. Work in the Anderson Mill Zone is anticipated to start in the fall of [...]

Forest North Drainage Project – October 3, 2017 Update

The Forest North Drainage Improvement Project continues in various areas of the neighborhood.  Monthly Updates are published, along with maps of the project [...]

Forest North Drainage Project – September 2017 Update

This week DeNucci Constructors, LLC continued asphalt patching this week for trench repairs in the Stillforest Zone.  They also continued concrete driveway [...]